FWDA Cleanup Schedule

jump over navigation barAerial photo of Fort Wingate.

The RCRA cleanup process requires the compilation of reports to document the nature and extent of contamination at the site. The following schedule indicates when the RCRA Facility Investigation (RFI) Work Plan for each parcel is scheduled for delivery to the New Mexico Environment Department under the requirements of the FWDA RCRA Closure Permit.

The RFI Work Plan describes the previous uses and conditions at the site and lays out a sampling plan if necessary for identifying the type and location of any remaining hazardous chemicals and materials.

Priority
Parcel
Number
General Description
Documents Submittal Date
1

Parcel 21 includes the TNT Workshop Area, TNT Leach Beds, electrical transformers, and the pre-1940s munitions storage area.

4/2/10
2

Parcel 11 includes a portion of the Administration Area, Sewage Treatment Plant, electrical transformers, and the pre-1940s munitions storage area.

4/28/10
3

Parcel 22 includes the TNT Workshop Area, Igloo Block D, electrical transformers, the pre-1940s munitions storage area, and land occupied by TPL.

4/18/13
4

Parcel 6 includes a portion of the Administration Area, TNT Workshop Area, Igloo Block B, Buildings 537, 542, electrical transformers, the pre-1940s munitions storage area, and land occupied by TPL.

9/28/11
5

Parcel 4 (west central) includes Igloo Block C and may include the pre-1940s munitions storage area). Parcel 4 may also include electrical transformers.

10/15/12
RAR

6

Parcel 23 (west central) includes the Central Landfill, and the pre-1940s munitions storage area. Parcel 23 may include electrical transformers

7/23/11

7

Parcel 10 (northwest) includes the Suspected POL Area, Former Administration and Utilities Area, and may include electrical transformers and the pre-1940s munitions storage area.

1/3/11
8

Parcel 5 (west central) includes former structures or buildings and may also include the pre-1940s munitions storage area. Parcel 5 may include electrical transformers.

9/28/11
9
8
Parcel 8 (northwest).
03/16/09 (n)
10

Parcel 16 (northeast corner) includes the Functional Test Range 2/3, buildings near Lake Knudson, Igloo Block K, and the pre-1940s munitions storage area. Parcel 16 may also include electrical transformers.

5/1/11
11

Parcel 13 (north central) includes the area around Lake Knudson, electrical transformers, and the pre-1940s munitions storage area

6/30/12
12

Parcel 18 (north central) includes the Eastern Landfill and the pre-1940s munitions storage area. Parcel 18 may include electrical transformers.

5/13/12
13

Parcel 12 (north) includes electrical transformers, and may include the pre-1940s munitions storage area.

11/16/10
RAR
14

Parcel 14 (north) may also include electrical transformers and the pre-1940s munitions storage area).

11/16/10
RAR
15

Parcel 7 (west of Administration Area) includes the Western Landfill, POL Disposal Area, Trash Burning Grounds, electrical transformers, and the pre-1940s munitions storage area.

11/01/13
16

Parcel 24 (northwest) includes Igloo Block A and the pre-1940s munitions storage area. Parcel 24 may include electrical transformers.

05/01/14
17
25
Parcel 25 (north) is located along Interstate 40.
06/19/09 (n)
18

Parcel 20 (southeast corner) includes the Functional Test Range 1, and is being used by the Missile Defense Agency (MDA). Parcel 20 may also include electrical transformers.

12/27/15
19

Parcel 2 (southwest corner, directly north of the OB/OD Area) includes Igloo Blocks C, H and J, Group C Landfill, Western Rifle Range, and is being used by the Missile Defense Agency (MDA). Parcel 2 may also include electrical transformers.

11/01/15
20

Parcel 19 (east central) includes Igloo Blocks D, E, F, and G, Building T-422 (Normal Maintenance Blg., Bomb and Shell Paint Blg.), electrical transformers, and the pre-1940s
munitions storage area.

05/01/16
21

Parcel 9 includes Igloo Block A and the pre- 1940s munitions storage area. Parcel 9 is being used by the Missile Defense Agency (MDA). Parcel 9 may include electrical transformers.

11/01/16
22

Parcel 3 includes the OB/OD Area SWMUs and AOCs.

1/15/13


RAR = Release Asessment Report
(n) = No Further Action


Get Adobe ReaderSome documents are included as Portable Document Format (PDF) Adobe Acrobat features. Please download Acrobat Reader to view them.