|
July 31, 2024 |
Final, Phase 2 RCRA Facility Investigation Work Plan, Parcel 11, Revision 2.0, April 30, 2024
2024 Interim Northern Area Groundwater Monitoring Plan, Revision 1, April 30, 2024
Final Phase 2 RCRA Facility Investigation Work Plan, Parcel 22, April 30, 2024
|
May 6, 2024 |
Final Groundwater Periodic Monitoring Report, January Through June 2022, Revision 1, December 22, 2023
Final Periodic Monitoring Report January Through June 2021, Rev. 1, November 8, 2023
Final Periodic Monitoring Report July Through December 2021, Rev. 1, November 8, 2023
|
May 1, 2024 |
Final 2023 CAMU Sampling Event Report, March 21, 2024
Northern Area Groundwater Phase 2 Supplemental RCRA Facility Investigation Work Plan, March 15, 2024
Final Administration Area Soil Vapor Investigation Work Plan, March 15, 2024
Final Work Plan Northern Area Sewer Line Investigation, March 15, 2024
Final Phase 2 RCRA Facility Investigation Work Plan, March 15, 2024
Approved Final Hazardous Waste Management Unit (HWMU) Progress Status Report 2022, Parcel 3, Feb 14, 2024
2024 Groundwater Monitoring Plan, January 26, 2024
Final Field Status Report Abandon and Plug Artesian Wells #68 and #69, January 1, 2024
Final Northern Area Groundwater RCRA Facility Investigation Report, Revision 3, December 20, 2023
|
July 21, 2023 |
HWMU Progress Status Report 2022 |
July 21, 2023 |
Final Igloo Exterior and Revetment RCRA Facility Investigation Sampling Work Plan |
June 30, 2023 |
Response to Approval with Modifications, Final Interim Measures Completion Report, Parcel 21 - Solid Waste Management Unit 1 - TNT Leaching Beds - Revised Report and RLSO |
June 30, 2023 |
Final Northern Area Groundwater RFI Report, Revision 3 |
June 8, 2023 |
Final RCRA Facility Investigation Report Parcel 7 Revision - Main Text, June 27, 2018
* Appendices
|
May 31, 2023 |
Final Parcel 3 Groundwater RCRA Facility Investigation Supplemental Sampling Work Plan, April, 18, 2023 |
March 31, 2023 |
Final Groundwater Periodic Monitoring Report January Through June 2022, March 13, 2023
* Appendices
Final Revised Work Plan Addendum, Abandon and Plug Artesian Wells #68 and #69, March 3, 2023
|
Feb. 9, 2023 |
Letter Work Plan for the Downhole Inspection for Well BGMW08 per the Approval w/ modifications on the July - December 2020 PMR dated July 25, 2022., Dec. 28, 2022
Final Groundwater Background Evaluation Fort Wingate Depot Activity McKinley County, New Mexico, Dec. 19, 2022
* Appendices
Final Northern Area Groundwater RCRA Facility Investigation, Dec. 19, 2022
* Appendices
|
Dec. 30, 2022 |
Final Work Plan Abandon and Plug Artesian Wells #68 and #69, June 15, 2022.
* Appendix
Approved Final Hazardous Waste Management Unit (HWMU) Progress Status Report, 2020 Hazardous Waste Management Unit (HWMU) Parcel 3, Oct. 14, 2021.
|
Oct. 28, 2022 |
Final Groundwater Periodic Monitoring Report July Through December 2021, Sept. 30, 2022.
* Appendices
Final Groundwater Periodic Monitoring Report July Through December 2020, Revision 3, Sept. 30, 2022.
* Appendices
Final Revision 2, Interim Measures Completion Report Parcel 21 SWMU 1 TNT Leaching Beds, Sept. 30, 2022.
* Appendices
2023 Interim Northern Area Groundwater Monitoring Plan, Revision 1, Aug. 23, 2022.
|
Apr. 28, 2022 |
Final Hazardous Waste Management Unit (HWMU) Progress Status Report 2020 Parcel 3, Jun. 11, 2021.
|
May 28, 2021 |
Response to New Mexico Environmental Department (NMED), second response to the Approval with Modifications Final Revision 1 Groundwater Periodic Monitoring Report (GWPMR) July – Dec 2018, Apr. 19, 2021.
* Appendices
Final Groundwater Periodic Monitoring Report January through June 2020, Mar. 30, 2021.
* Appendices D_E
|
Apr. 30, 2021 |
Military Munitions Maps and Table, CY 2020, Mar. 15, 2021
Second Response, Approval with Modifications, Response to Approval with Modifications,
Final Revision 1 Groundwater Periodic Monitoring Report, July Through December 2018, Feb. 16, 2021
* Revision1_GWPMR_July_Dec_2018_appendices
|
Mar. 31, 2021 |
Final Revision 1 Hazardous Waste Management Unit Progress Status Report, 2012-2018, HWMU, Parcel 3, Mar. 22, 2021
Approved Final, Revision 1, Parcel 3 Groundwater Background Wells and Replacement Monitoring Wells Installation WP, Mar. 15, 2021
Earth Covered Magazine (ECM) Inventory of Waste Military Munitions at Ft. Wingate NM, Quarterly Report, Mar. 1, 2021
Final Groundwater Background Evaluation, Mar. 1, 2021
|
Oct. 30, 2020 |
Final Revision 1 Groundwater Periodic Monitoring Report July through December 2018, April 15, 2020
|
July 15, 2020 |
Final Hazardous Waste Management Unit Progress Status Report, 2019, HWMU, Parcel 3, June 23, 2020
Final Revision 1 Parcel 3 Groundwater Background Wells and Replacement Monitoring Wells Installation Work Plan, June 12, 2020
Final Hazardous Waste Management Unit Status Report 2012-2018, HWMU, Parcel 3, May 19, 2020
Final 2019 Interim Northern Area Groundwater Monitoring Plan Version 11, Apr. 1, 2020
|
Apr. 2, 2020 |
Military Munitions Maps and Table for 2019, FWDA, Mar. 19, 2020
Final Work Plan Inner Fence, Parcel 3, Revision 3.0, Feb. 28, 2020
Final Asbestos Survey Report Parcel 2, 6, 7, 13, 16, 19, 20, 22, & 23 - FWDA, Feb. 7, 2020
• Asbestos survey report submittal letters
|
Jan. 30, 2020 |
Final Groundwater Background Evaluation Report, Dec. 26, 2019
• Final GW Background Eval Appendices
Final Interim Measures Completion Report Parcel 21 - Solid Waste Management Unit 1 - TNT Leaching Beds, Dec. 19, 2019
• IMCR_P21_SWMU1_appendices
Final Parcel 3 Groundwater Background Wells and Replacement Monitoring Wells Installation Work Plan, Dec. 18, 2019
|
Dec. 23, 2019 |
Letter Work Plan, Downgradient Alluvial Aquifer Investigation & Installation of One Additional Well FWDA, Dec. 11, 2019
Final Groundwater Periodic Monitoring Report, July - December 2018, November 30, 2019
Final Revision 1 Groundwater Periodic Monitoring Report, January - June 2018, Oct. 28, 2019
|
Oct. 30, 2019 |
Final Work Plan, Inner Fence, Parcel 3, Oct. 15, 2019
|
Oct. 16, 2019 |
Final Rev. 2 Permittee-Initiated Interim Measures Report, Parcel 24 - Igloo Block A, Sept. 27, 2019
|
Aug. 29, 2019 |
Final 2017 Interim Facility-Wide Groundwater Monitoring Plan, Version 10, Revision 1, July 27, 2019
• Appendices_Final_2017_Interim_FW_GW_Monitoring_Plan_Ver 10_Rev 1.zip
Final Revision 1 Groundwater Periodic Monitoring Report, July - December 2017, Feb. 28, 2019
|
June 25, 2019 |
Final Rev. 1 Permittee-Initiated Interim Measures Report Parcel 24 Igloo Block A, May 29, 2019
|
May 31, 2019 |
Final RCRA Facility Investigation Phase 2 Work Plan Parcel 23 Revision 1.0 Fort Wingate Depot Activity, McKinley County, New Mexico, Apr. 29, 2019
Ground Water Periodic Monitoring Report January Through June 2018, Apr. 5, 2019
|
Apr. 30, 2019 |
Final Revision 1 Parcel 3 Groundwater RCRA Facility Investigation Report, Mar. 31, 2019
Final RCRA Facility Investigation Report Parcel 6, Revision 1.0, Mar. 29, 2019
|
Oct. 16, 2018 |
Final Groundwater Periodic Monitoring Report July through December 2017, July 13, 2019
|
August 29, 2018 |
Final RCRA Facility Investigation Report Parcel 13, Aug. 3, 2018
Final RCRA Facility Investigation Phase 2 Work Plan Parcel 23, Jul 24, 2018
Final RCRA Facility Investigation Phase 2 Work Plan Parcel 11 Revision 1.0, Jul 20, 2018
Final Investigation Report Igloo Block A Parcel 9, Jul 1, 2018
Final Parcel 9 Igloo Block A Investigation Report_FWDA Submission Cover Ltr. 27 July 2018
Final Parcel 9 Igloo Block A Investigation Report_FWDA_27 July 2018
Final Summary Report of Historical Information Parcel 9, Jun 8, 2018
|
August 24, 2018 |
Final Permittee-Initiated Interim Measures Report Parcel 6 Revision 1.0, Jul 27, 2018
|
July 30, 2018 |
Final Parcel 3 Groundwater RCRA Facility Investigation Report (Southern Area), June 26, 2018
|
Apr. 11, 2018 |
Approved Final Revision 2 Interim Measures Work Plan Parcel 21 SWMU 1- TNT Leaching Beds, Sept. 29, 2017
|
Mar. 19, 2018 |
Final Permittee- Initiated Interim Measures Report Parcel 16 Revision 1.0, Dec. 22, 2017
Final Fort Wingate Depot Activity Groundwater Monitoring Northern Area Background Well Installation Letter Work Plan, Sep. 18, 2017
|
Mar. 05, 2018 |
Final Revision 1 Groundwater Periodic Monitoring Report January Through June 2016, Nov. 30, 2017
Final Work Plan Inner Fence Parcel 3, Nov. 29, 2017
|
Jan. 10, 2018 |
Final Permittee- Initiated Interim Measures Report Parcel 16 Revision 1.0, Dec. 22, 2017
|
Nov. 13, 2017 |
Final 2017 Interim Facility-Wide Groundwater Monitoring Plan
|
Oct. 11, 2017 |
Final Groundwater Periodic Monitoring Report January Through June 2017, Sept 19, 2017
|
Sept. 28, 2017 |
Final Facility Wide Groundwater Periodic Monitoring Report July Through December 2016 Submission Conducted in October 2016 FWDA, Aug. 31, 2017
|
Aug 30, 2017 |
Final Corrective Action Management Unit (CAMU) Biennial Soil Sampling Event Letter Report, July 27, 2017
Revised Final Version 01 Installation Spill Contingency Plan (ISCP), Apr 18, 2017
|
May 3, 2016 |
GPMR_Jul-Dec2015_ArmyDraft
GPMR_Jul-Dec2015_ArmyDraft
AppA
AppB
DQE_ReportFall2015
280-76166-1
280-76166-2
280-76166-3
280-76216-1
280-76216-2
280-76216-3
280-76268-1
280-76268-2
280-76268-3
280-76331-1
280-76331-2
280-76331-3
280-76405-1
280-76405-2
280-76475-1
280-76475-2
280-76532-1
280-76532-2
280-77373-1
280-76048-1
280-76048-2
280-76114-1
280-76114-2
J76216-1 Std_Tal_L4_Package_Mini Rev(2) Final Report
J76216-2 Std_Tal_L4_Package_Mini Final Report
J76216-3 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76268-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76268-2 Std_Tal_L4_Package_Mini Final Report
J76268-3 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76331-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76331-2 Std_Tal_L4_Package_Mini Final Report
J76331-3 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76405-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76405-2 Std_Tal_L4_Package_Mini Final Report
J76475-1 Std_Tal_L4_Package_Mini Final Report
J76475-2 Std_Tal_L4_Package_Mini Final Report
J76532-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76532-2 Std_Tal_L4_Package_Mini Final Report
J77373-1 Std_Tal_L4_Package_Mini Final Report
J76048-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76048-2 Std_Tal_L4_Package_Mini Final Report
J76114-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76114-2 Std_Tal_L4_Package_Mini Final Report
J76166-1 Std_Tal_L4_Package_Mini Rev(1) Final Report
J76166-2 Std_Tal_L4_Package_Mini Final Report
J76166-3 Std_Tal_L4_Package_Mini Rev(1) Final Report
FtWingate_AppendixD_Nov2015_Data
Appendix C2B
Appendix C2C
Appendix C2D
Appendix D SSHP
Appendix F QSM
Appendix G_NMED
Final FWGMP_Vers 8 Main Text
Final FWGMP_Vers 8 Main Text.pdf.accreport
GWMP Rev 8-NMED CRT ltr 4Jan2015[1]
Appendices
Appendix C-1
Appendix C2A
WD-11 Well Plugging Record - Wingate 89
WD-11 Well Plugging Record - Wingate 90
WD-11 Well Plugging Record - Wingate 91
WD-11 Well Plugging Record - FW26
Q91_FIG 11_March_20160317
Q91_FIG_12_March_20160317 (002)
MEC Map submission ltr March 2016
CRP_Table_5_Military_Munitions_Summary_Table_March 2016
Nov_16_2015Army_ Draft_HWMU_ Removal_ Report
Army Draft_HWMU Removal Report_Appendices Only
GPMR_Jan-June2015_Final
AppA
AppB
AppC_DQE_Report
Attach1
J67366-1 Std_Tal_L4_Package_Mini Final Report
J67366-2 Std_Tal_L4_Package_Mini Final Report
J67438-1 Std_Tal_L4_Package_Mini Final Report
J67438-2 Std_Tal_L4_Package_Mini Final Report
J67484-1 Std_Tal_L4_Package_Mini Final Report
J67484-2 Std_Tal_L4_Package_Mini Final Report
J67561-1 Std_Tal_L4_Package_Mini Final Report
J67561-2 Std_Tal_L4_Package_Mini Final Report
J67662-1 Std_Tal_L4_Package_Mini Final Report
J67662-2 Std_Tal_L4_Package_Mini Final Report
J67711-1 Std_Tal_L4_Package_Mini Final Report
J67711-2 Std_Tal_L4_Package_Mini Final Report
J67267-1 Std_Tal_L4_Package_Mini Final Report
J67267-2 Std_Tal_L4_Package_Mini Final Report
J67316-1 Std_Tal_L4_Package_Mini Final Report
J67316-2 Std_Tal_L4_Package_Mini Final Report
EvapNorthTankSedSampling
FtWingate_AppendixE_Apr2015_Data
Oct_20_2015_Sampling_Letter_Contamination_for_HWMU_Removal
Oct_22_2015_Well _340 _Assessment _Report
Oct_22_2015_Well_ 2_ Assessment _Report
Oct_28_2015_FW_ GW_ April _2015_ report
Oct_28_2015_GPMR_Replacement_Page_Submittal-Letter
Oct_30_2009_ Environmental Information Management Plan
Sep_18_2015_404_Permit_Pika_4345_2014dec-Agent signed
Sept_9_2015_Disapproval_Final_ Facility_Wide_GW-Revision 6
Sept_9_2015_Disapproval_Tech_Memorandum_GW-2015
Sept_9_2015_Fee_Assessment_Final_GW_July_Thru_Dec_2014
Sept_16_2015_NMED_GW_Approval_wMods_GWPM_Report
Sept_21_2015_physical_security_inspection_report
2012 Nationwide permits conditions district engineers decision further Info
April_1_1968 Site Study for a Water Wall
BCT meeting and sign in sheet Feb_5_1997
Dec 30 2015 Extension Request for GW Background Evaluation
Dec 30 2015 Extension Request for TNT Leaching Bed Soil Borring Results & Development of site specific DAF
Dec 30 2015 Extention Request 2015 Interim Measures FW GW monitoring plan Rev_8
Dec_10_2015_15th_missile_launch_out of fort wingate
Dec_14_2015_Army_says_patriot_missile_test_a_success_article
Dec_18_2015_Army_draft__Interim_Measures_WP_areas_of_concern_solid_waste_management_units_kickout_area - Shortcut
Dec_22_2015_Extension_request_for_three_documents_FWDA
Dec_22_2015_Revised interim FW GW monitoring plan at fwda
Feb_1_2002_SW_SWPPP
Feb_4_2016_Waste Management Plan & Haradous Waste Contingency Plan
Feb_22_2010 Military Munitions Summary Table
Feb_23_2016_Army_GW_Background_Tech_Memo_Extension_Request (003)
Fee assesments Jan_14_2016
Jan_1_2016_Development of soil screening levels & Site specific DAF
Jan_4_2016 Interim FW GW monitoring plan FWDA
Jan_27_2012 Military Munitions Summary Table
Jan_27_2016_Development of Soil screening levels
Jan_27_2016_FWDA_TNT_leaching_Bed_soil_Boring_Test_results_DAF
Jan_28_2016 Administrative Completeness Deterimination
July_1_1969 Drilling _testing of Well 340
July_1_2015_Risk_Assessment_Guidance for_SI_and_Remediation
July_15_2011 Interim Facility Wide GW Monitoring Plan Version 5
June_1_1997 SWPPP General Storm Water Discharge Permit
June_13_2015 Ordnance Explosives off Post Removal Action Report
Mar_1_2005 Collection Methos & Lab Processing Firing Points
Mar_1_2005_ Estimating Energetic Residue Loading on Military Artillery Ranges
March _1_2016 EMC Inventory of WMM Invironemtnal Remediations Efforts FWDA
March 1 2016 Second extention Requestion for GW Background Eval
March 30 2016 Fee Assessment
March 30 2016Ground water
March_1_1988 Master Plan Report
March_1_1990 Enhanced Preliminary Assessment Report
March_4_2016 Fee Assesment
March_24_2016_Extension Request Revised Final Northern GW RCRA
May_1_1993 UST Bldg 6 Area GW Monitoring Program
May_5_2015_BCT_Meeting FINAL
May_20_15_Revised Letter Work Plan Soil Testing and Removal at the Former Water Tower and Tank Sites at FWDA
MDA_ July 2 1997
Media_2016
Multi parcel 1997
Nov_1_2005_ Identity and distribution of residues of energetic compounds at military live fire training ranges
Nov_6_1992 F Technical plan for the Environmental Investigation
Nov_6_1992 Final Health Plan and Safety Plan for the Environmental Investigation
Nov_7_14_Well_Plugging_Plan_of_Operations_2
Nov_7_2014_Well_Plugging_Plan_of_Operations_1
Nov_18_1996_Site Health and Safety Plan Drilling Services
Oct_1_2015_Final_GW_Supplemental_RCRA_Facility
Oct_1_2015_NMED_Annual_Fee_
Oct_7_2015_Army_PIIM_WP_Extension_Request
Oct_14_2015_Army _Draft_ Interim _Measures_ Work Plan_
Oct_20_2015_final_Sampling_Results_for_Area_Contamination_HWMU_Removal
Oct_20_2015_Extention_WP_Parcels_2_9_19
Oct_29_2015_FWDA_ Parcel_ 2_Extention_Request_RFI_Work_Plan
Aug_24_2015_NMED_P2_Disapproval_RFI_WP
Nov_1_2015_Parcel_3_Groundwater_Quality_Control_Plan
Nov_1_2015_Project_Management_Plan_ Parcel _3 _Groundwater _RFI
Oct_12_2015_Draft PMP Parcel 3 Groundwater RFI_
Oct_12_2015_Parcel 3_Groundwater_RCRA_Facility_Investigation_QC_Plan
Oct_12_2015_Parcel_3 _Accident_Prevention_Plan_Groundwater_RCRA
Dec_31_2015_army_draft_P3_GW_rcra_facility_investigation_wp
Nov_1_2015_Parcel_ 3_Accident_Pervention_Plan_GW_RCRA_Facility
FWDA_Army Draft_HWMU Removal Report - Appendices K - N
FWDA_Army Draft_HWMU Removal Report - Appendix J
FWDA_Army Draft_HWMU Removal Report - Text Only
FWDA_Army Draft_HWMU Removal Report - Appendices A - D
FWDA_Army Draft_HWMU Removal Report - Appendices E - I
Final DRAFT Parcel 3 RFI WP 102315 Text Only
Final DRAFT Parcel 3 RFI WP 102315_WP_only_no_appendices
Final DRAFT Parcel 3 RFI QAPP 102315 Text Only
F_SRHI_OBOD_P3_Appendix B
F_SRHI_OBOD_P3_Appendix C
F_SRHI_OBOD_P3_Appendix D
F_SRHI_OBOD_P3_Appendix E
F_SRHI_OBOD_P3_Appendix F
F_SRHI_OBOD_P3_Appendix G
F_OBOD_CP_IA_SOIL
F_OBOD_CP_IB_GW Appendix F for Appendix A
F_SRHI_OBOD_P3
F_SRHI_OBOD_P3_Appendix A
Appendix C - CO_20131218_BLASE_BRAC_NMED
Parcel_3 Historical Analytical Results
Final DRAFT Appendix D - Parcel 3 RFI QAPP
FWDA Parcel 3 SWMUs and AOCs RFI Schedule
Ft Wingate Draft RTC
Parcel_6_2016
Oct_29_2015_Extention_Request_Parcel_9_RFI_WP
Jan_7_2016_tribal_review_of_Final_P11_phase_2_RCRA_facility_investigation_fwda
Oct_22_2015Amec_ Parcel_ 11_ WP _submission_cover_letter
Oct_29_2015_Final_P11_Phase_2_RFI_WP
Jan 7 2016 Disapproval Final WP P11 SWMU 10 & 40 FWDA
June_3_2015_USEPA_Approval_ Email_P13_Water_Tower_Soil_Removal_Work_Plan
Feb_17_2016 Extention Request P16 PIIM Completion
Dec_15_2015_Parcel_18_Petition_Letter
Oct_29_2015_Parcel_ 19_Extention_Request_RFI_WP
March_9_2016 Disapproval Final RCRA Facility Investigation WP P20
Draft_EPP_FWDA_Parcel21_24_Rev1
Cover_Ltr_to_Draftl_EPP_SPCC_WMP_HWCP
IMWP_FWDA_Parcel21_Appendix_D_Only
2016 03-11 Draft IMWP Transmittal Letter
Draft_IMWP_FWDA_Parcel21_Rev1
FinalR1_P21_PIIM_WkPlan_102815
Sep_18_2015_Extension_Request_for_Permittee_Initiated_Interim_Measures_WP_Parcel_21
Oct_22_2015_Amec_ Parcel_ 21_ WP_ Rev_ 1_ submission_ cover_ letter
Jan_7_2016_extention_request_revised_P22_wp_fwda
Nov_24_2015_Disapproval_F_WP_P22_Solid_Waste_Management_Units_12_27_70
Jan 12 2016 Second extension Request for P22 Revised PIIM WP FWDA
Nov_17_2015_Parcel _23 _Extension_ Request_Revised_Phase_2
Oct_20_2015_RCRA facility Investigation Phase 2 WP P23
Dec 22 2015 Extension Request P23 Revised Phase II RCRA Facility Investigation WP
Jan 7 2016 Extention Request for Revised P23 Phase II RFI WP FWDA
Jan 19 2016 2nd extention request for the P23 Phase II RCRA Facility Investigation WP
Parcel 25 DTS Assignment
Nov_20_2015Parcel 25 DTS assignment
|
Jul 23, 2015 |
July_23_2015_Deviation Approval and Risk Acceptance Document P3
|
Jul 22, 2015 |
April_28_2015_Final Interim Facility-Wide Groundwater Monitoring Plan, Version 8, Revision 1
|
Jul 15, 2015 |
February_26_2015_Final Accident Prevention Plan for KOA MEC Removal and Surface Clearance
February_24_2015_Final Permittee-Initiated Interim Measures Work Plan for Parcel 22
February_13_2015_Final Storm Water Pollution Prevention Plan for Parcel 21
January_9_2015_Final_Project Management Plan for Parcels 11, 20, and 22
November_25_2014_Final_Project Management Plan for Parcels 21 and 24
|
Jul 07, 2015 |
July_1_2015_Final Stormwater Pollution Prevention Plan for Permittee-Initiated Interim Measures Parcels 6, 13, 16, 21, and 22
July_1_2015_Final Environmental Protection Plan for Parcels 6, 13, 16, 21, and 22
|
Jun 11, 2015 |
February_6_2015_Final Work Plan Munitions and Explosives of Concern Removal and Surface Clearance in the Kickout Area
May_4_2015_Final-Permittee Initiated Interim Measures Work Plan Parcel 6 Revision 1.0
|
Jun 09, 2015 |
Wingate Ordnance Depot 1850-1958
March_18_2015_Final Groundwater Technical Memorandum Background Evaluation Revision 1
January_30_2015_Final Groundwater Supplemental RCRA Facility Investigation Work Plan
February_20_2015_Final RCRA Facility Investigation Work Plan Parcel 2
February_27_2015_Final RCRA Facility Investigation Work Plan Parcel 9
February_13_2015_Final RCRA Facility Investigation Work Plan Parcel 19
March_27_2015_Final Groundwater Periodic Monitoring Report July through December 2014
|
Jun 01, 2015 |
April_22_2015_Final Work Plan for Parcel 11 SWMU 10 and 40
May_6_2015_Final Permittee-Initated Interim Measures Work Plan for Parcel 16, Revision 1.0
|
May 28, 2015 |
May_31_2015_Final RCRA Facility Investigation for Parcel 22, Revision 2.0
|
May 06, 2015 |
Wingate Centennial History
The History of Fort Wingate H. James
|
Feb 26, 2015 |
Final Investigation and Remediation Completion Report for Parcel 18 Eastern Landfill, Dec 12, 2014
Final Permittee - Initiated Interim Measures for Parcel 24 Igloo Block A, Oct 22, 2014
Final Groundwater Periodic Monitoring Report January through June 2014, Sep 26, 2014
Final Technical Memorandum Groundwater Background Evaluation, Sep 5, 2014
|
Sep 15, 2014 |
Approved Final - RCRA Facility Investigation Report, Parcel 10B-FWDA , Mar 19, 2012
FINAL of the Release Assessment Report for Parcel 10 Volume 1-Main Report, Appendices A-E, Version 3.0-FWDA, Oct 1, 2009
'Facility-Wide Groundwater Periodic Monitoring Report for January, April, July 2008, Version 1, RCRA Permit No. 3213820974-FWDA, Dec 1, 2008
'Base Realignment & Closure Installation Action Plan, FY 2008-FWDA, Nov 1, 2008
'Repair of Earth Covered Magazines-FWDA, July 1, 2008
Summary Report of Historical Information, Parcel 22 – UPDATED Final-FWDA, Jun 9, 2008
Aerial Photographic Analysis, Vol. 1 Main Report & Appendix, Sep 1, 2006
|
Aug 19, 2014 |
'Certification of Completion West & North Boundary Fence, Parcel 3 - FWDA, Sep 11, 2006
'Identity and Distribute of Residues of Energetic Compounds At Military Live-Fire Training Ranges-FWDA, Nov 1, 2005
'Site Information - FWDA, Aug 30, 2005
'Final Report Western Landfill, Vol I & II-FWDA, July 1, 2005
'Inspection and Return of D Area Magazines-FWDA, July 1, 2005
'PCB Inventory-FWDA, Jan 1, 2005
Examination of Protocols for the Collection of Munitions-Derived Explosives Residues on Snow Covered Ice, Apr 1, 2005
'Collection Methods & Laboratory Processing Samples from Donnelly Training Area Firing Points, Alaska, 2003, Mar 1, 2005
'Estimating Energetic Residue Loading on Military Artillery Ranges-FWDA, Mar 1, 2005
|
July 24, 2014 |
'Final - Groundwater Periodic Monitoring Report for July thru December 2013 - Main Text and Appendices A-D, Apr. 22, 2014
'Data Validation Report for Building 522, Sampling Collected on July 12, 2010 - FWDA , Jan 1, 2011
'Data Validation Report for Building B530, Sampling Collected on September 16, 2010 - FWDA, Feb 1, 2010
'Final Work Plan, Installation Fencing the Western and Northern Boundary of Parcel 3-FWDA, Apr 1, 2006
'Draft Final RCRA Facility Investigation Report, TNT Leaching Beds - FWDA, Nov 26, 2001
'Work Plan Environmental Characterization, Buildings 542 and 600 - Final-FWDA, Nov 15, 2000
'Draft - Ballistic Missile Defense Organization Environmental Assessment (Launch Complex), June 1, 1999
'Specification for Environmental Protection Shelter, HERA Support Program - FWDA, Apr 1, 1996
'Final Resource Conservation and Recovery Act Interim Status Closure Plan-FWDA, Mar 1, 1993
Final Supplemental Health and Safety Plan – Field Investigation, Preparation of RI/FS Report, and Accelerate Transfer of the SW Property, Igloo Blocks A, B, and C and the Ballistic Missile Site Areas-FWDA , Dec 18, 1992
'RCRA Part B Permit Application for Open Burning/Open Detonation, Volume 2 - FWDA, Nov 1, 1988
|
June 30, 2014 |
Final - RCRA Facility Investigation Report Parcel 11, Revision 2, Volume 1,2,3 - FWDA , May 23, 2014
'Final Report - Garage Pile Analyses Sampling Report for Parcel 10 - FWDA, Dec. 19, 2012
' Field Investigation Report, Building 11-FWDA, Jan 22, 2004
'Closed Transfering & Transfered Range & Site Inventory Report-FWDA - Final, June 1, 2003
'Environmental Condition of Property, Parcel 6 & 22 - FWDA, Jan 1, 2003
'Risk Assessment Technical Memorandum, OB/OD Areas – Final-FWDA, Sept. 15, 2000
'MOA Environmental Team - FWDA, Aug. 24, 2000
'Sampling & Analysis Plan for Removal and Disposal of Group C and Central Landfills - FWDA, Dec. 29, 1998
'Geohydrologic Study No. 38-26-8916-90 Storage Yard West of Administration Area-FWDA, Apr 1, 1990
'RCRA Part B Permit Application for Open Burning/Open Detonation at FWDA, Nov. 1, 1988
'Site and Safety Plan, June 1, 1987
|
May 14, 2014 |
Final RCRA Facility Investigation Report Parcel 16, Main Text and Appendices, May 9, 2014 |
May 8, 2014 |
Final - Permittee-Initiated Interim Measures Report for Parcel 4A, Area of Concern 29 - FWDA , Apr. 15, 2014 |
Apr. 9, 2014 |
RCRA Class 3 Permit Modification, December 1, 2005 (Revised: April 2014), Apr. 7, 2014 |
Mar 31, 2014 |
Military Munitions Map and Table for 2014 - FWDA, Mar. 7, 2014 |
Feb 4, 2014 |
Final Release Assessment Report Parcel 24, Jan 31, 2014 |
Jan 15, 2014 |
Final-2014 Interim Measures Facility-Wide Groundwater Monitoring Plan, Version 7, Jan 13, 2014 |
Nov 19, 2013 |
Spill Prevention, Control, and Countermeasures Plan HWMU, Parcel 3, Nov. 14, 2013 |
Oct 22, 2013 |
Final Groundwater Periodic Monitoring Report, January thru June 2013, Main Text and Appendices A-D - FWDA , Sept. 18, 2013 |
Sept 30, 2013 |
Final Stormwater Pollution Prevention Plan Parcel 18, Eastern Landfill - FWDA (Revised on 08/23/2013 with change page 2-5), Aug 7, 2013
Final RCRA Facility Investigation Report Parcel 11, Revision 1.0 - Volumes 1 - 3 - FWDA (Approved with modifications 9/17/2013) , Mar. 29, 2013
Approved Final Release Assessment Report for Parcel 12 & 14, Jan 13, 2011
Community Relations Plan, Annual MMRP Map Update - Figure 11, Figure 12, Table 5 - March 2010 Submittal-FWDA , Mar 4, 2010
|
Aug 29, 2013 |
Final RCRA Facility Investigation Report Parcel 16, Main Text and Appendices, Aug. 16, 2013
Final RCRA Facility Investigation Report Parcel 11, Revision 1.0 - Volumes 1 - 3 - FWDA , Mar. 29, 2013
Final Groundwater Periodic Monitoring Report for April 2012, Version 1 - FWDA , Jan. 28, 2013
|
July 31, 2013 |
'OB/OD Hazardous Waste Contingency Plan, Rev. 1 - FWDA, Jun. 25, 2013
'Approved Final RCRA Facility Investigation Phase 2 Work Plan, Parcel 21 - FWDA, Aug. 30, 2012, Approved Jun. 20, 2013
'Final RCRA Facility Investigation Summary Report of Historical Information Parcel 16 - FWDA, Jan. 10, 2011
|
July 30, 2013 |
Approved Final Phase 2 Soil Background Report - FWDA , Feb. 5, 2013
Approved Jul. 23, 2013
|
June 24, 2013 |
Storm Water Pollution Prevention Plan HWMU, Parcel 3 - Revision 6.0 - FWDA, June 13, 2013 |
May 29, 2013 |
Final - Groundwater Periodic Monitoring Report, July 2012 thru December 2012- FWDA , May 21, 2013 |
Apr 22, 2013 |
Spill Prevention Control and Countermeasures Plan HWMU, Parcel 3 - FWDA, Apr, 18, 2013
Final CAMU Sampling Work Plan HWMU, Parcel 3 - Revision 1.0 - FWDA, Apr. 11, 2013
Draft Final Work Plans Groundwater Investigation Eastern Landfill: 1.Sampling and Analysis Plan; 2. Site Safety and Health Plan-FWDA, Jan 1, 2004
|
Apr 16, 2013 |
Storm Water Pollution Prevention Plan, Revision 5, HWMU Parcel 3 - FWDA, Apr. 10, 2013
Site Assessment Report – Final Draft-FWDA, Feb. 1, 1998
Final Remedial Investigation/Feasibility Study and RCRA Correction Action Program Document Vol. 1 thru 10-FWDA, Nov. 1, 1997
|
Mar 22, 2013 |
'Base Realignment & Closure Installation Action Plan FY 2012 FWDA, Mar 23, 2013 |
Feb 28, 2013 |
'Approved Final - Removal Work Plan HWMU, Parcel 3 - FWDA, Feb. 19, 2013
'Final Phase 2 Soil Background Report - FWDA, Feb. 11, 2013
'HAFB Fact Sheet (RCRA Post Closure Permit), Mar. 10, 2011
'Collective Summary for Ft. Wingate Depot Activity (Archeological) - FWDA, Dec. 1, 1995
|
Feb 21, 2013 |
'Final Investigation and Remediation Work Plan Parcel 18, Eastern Landfill, Revision 1 - FWDA, Feb. 6, 2013 |
Feb 13, 2013
|
Community Relations Plan Annual MMRP Map Update Figure 11, Figure 12, Table 5, 2012 Activities - FWDA, Mar. 1 2013
Final CAMU Sampling Work Plan, HWMU Work Plan Removal - FWDA, Feb. 6, 2013
|
Jan 30, 2013 |
Army Final - Water Tower Demolition Report - FWDA, Jan. 21, 2013
Final - Report of Investigation for Potential Environmental Areas of Concern - FWDA, Nov. 11, 2007
|
Jan 16, 2013 |
Final RCRA Facility Investigation Work Plan and HISD, Parcel 7 - FWDA, Jan. 3, 2013
2011 and 2012 Monitoring Well Installation and Abandonment Report, Version 1 - FWDA, Dec. 28, 2012
Final - Revision 1, Removal Work Plan HWMU, Parcel 3 - FWDA, Dec. 19, 2012
|
Nov 30, 2012 |
Summary Report of Historical Information, Parcel 11-FWDA, June 19, 2009 |
Oct 19, 2012 |
Final Interim Facility-Wide Groundwater Monitoring Plan, Version 6 - FWDA, Oct. 15, 2012
Final RCRA Facility Investigation Work Plan, Parcel 16 - FWDA, Oct. 1, 2012
Final RCRA Facility Investigation Report Parcel 6, Main Text & Appendices - FWDA, Sept. 30, 2012
|
Oct 17, 2012 |
Final Release Assessment Report Parcel 4A, Revision 2.0 - FWDA, Oct. 11, 2012
Final RCRA Facility Investigation Phase 2 Work Plan, Parcel 21 - FWDA, Aug, 30, 2012
Addendum to the RCRA Facility Investigation Report, Parcel 21 - FWDA, April 24, 2012
|
Sept 26, 2012 |
RCRA Facility Investigation Report, Parcel 21, Approved Final - FWDA, 8/27/2012 |
July 26, 2012 |
Environmental Survey of Fort Wingate Depot Activity-FWDA, Sept.1, 1981 |
July 17, 2012 |
Phase 2 Soil Background Work Plan - FWDA, Jan 20, 2012
Summary Interviews-FWDA, Feb 20, 2007
|
June 29, 2012 |
Storm Water Pollution Prevention Plan, Revision 4.0, HWMU Parcel 3 - URS, 06/18/2011
Facility Wide, Groundwater Periodic Report for Oct. 2008 – Jan. 2009 Version 1 - FWDA, USACE Albuquerque District, 06/01/2009
Wingate Ordnance Depot, Facilities Data - FWDA, 05/1/1961
|
May 30, 2012 |
Final Groundwater Periodic Monitoring Report for April thru October 2011 - FWDA, 5/14/2012 |
May 17, 2012 |
Final Investigation and Remediation Work Plan, Parcel 18, Eastern Landfill - FWDA, 5/10/2012 |
May 17, 2012 |
Final RCRA Facility Investigation Work Plan, Parcel 13 - FWDA, 5/10/2012 |
May 11, 2012 |
Risk Assessment Guidance for Site Investigations and Remediation, February 2012, New Mexico Environment Department, 2/1/2012 |
Apr 17, 2012 |
Final RCRA Facility Investigation Parcel 23, Main Text & Appendices, Version 1.0 - FWDA, 4/30/12 |
Mar 21, 2012 |
Final - RCRA Facility Investigation Report, Parcel 10B-FWDA, 3/19/12 |
Feb 28, 2012 |
Community Relations Plan Annual MMRP Map Update, Figure 11, Figure 12, Table 5- 2011 Activities, March 2012 Submittal - FWDA, |
Dec 29, 2011 |
Storm Water Pollution Prevention Plan, Revision 3, HWMU Parcel 3 - FWDA, 12/5/2011 |
Dec 5, 2011 |
Final-RCRA Facility Investigation Report, Parcel 22, Main Text & Appendices- FWDA, 12/9/2011
Storm Water Pollution Prevention Plan, Revision 2, HWMU Work Plan and Removal - FWDA, Nov 9, 2011
|
Nov. 10, 2011 |
Final - Removal Work Plan HWMU, Parcel 3 - FWDA, Nov. 9, 2011
Final Release Assessment Report Parcel 4A, Revision 1.0 - FWDA, Nov. 7, 2011
|
Oct. 6, 2011 |
RCRA Facility Investigation Work Plan for Parcel 10B, Vol. One - Main Report, Appendix A, Version 2.0 - FWDA, June 1, 2010 |
Sept 29, 2011 |
Final RCRA Facility Investigation Report Parcel 11, Volume 1-Main Text, July 31, 2011
Facility-Wide Groundwater Periodic Monitoring Report for April 2010 to July 2010 - FWDA, Dec. 20, 2010
Final Release Assessment Report Parcels 12 & 14, NMED Revision - FWDA, Nov. 16, 2010
|
July 25, 2011 |
Final - Groundwater Periodic Monitoring Report for October 2010 through January 2011, Version 1 - FWDA, July 15, 2011
Final - Interim Facility-Wide Groundwater Monitoring Plan, Version 5 - FWDA, July 15, 2011
Storm Water Pollution Prevention Plan HWMU Parcel 3, Revision 1.0 - FWDA, July 8, 2011
FWDA RCRA Permit Issued December 1, 2005, Modified June 27, 2011.
|
June 27, 2011 |
Final - Accident Prevention Plan HWMU, Parcel 3 - FWDA, May 26, 2011
Final - Auxiliary Tasks Work Plan HWMU, Parcel 3 - FWDA, May 12, 2011
Final-RCRA Facility Investigation Work Plan Parcel 16 - FWDA, May 2, 2011
|
May 31, 2011 |
Monitoring Well Installation and Abandonment Work Plan - FWDA, April 12, 2011 |
April 29, 2011 |
Final - NMED Revised RCRA Facility Investigation Work Plan for Parcel 6 - FWDA, Mar. 30, 2011
Community Relations Plan Annual MMRP Map Update Figure 11, Figure 12, Table 5 - 2010 Activities - March 2011 - FWDA, Mar. 28. 2011
|
February 28, 2011 |
Final Quality Assurance Surveillance Plan HWMU _ FWDA, Jan. 20, 2011
Final Project Management Plan HWMU - FWDA, Jan. 20, 2011
Site-Specific Final Report, OB/OD Unit Kickout Investigation Report dated October 2009-FWDA, Oct. 1, 2009
RCRA Facility Investigation Work Plan, Parcel 11, Revision – Final-FWDA, Jun. 19, 2009
Release Assessment Report, Parcel 4A, Igloo Block C – FINAL-FWDA, Mar. 1, 2009
Release Assessment Report, Parcel 22 – Final-FWDA, Jun. 9, 2008
Interim Facility-Wide Ground Water Monitoring Plan Version 2-FWDA, Mar. 8, 2008
|
January 28, 2011 |
Final RCRA Facility Investigation Report Parcel 21 - FWDA, Jan 14, 2011
Facility-Wide Groundwater Periodic Monitoring Report for October 2009 to January 2010, Version 2 - FWDA, Jan 7, 2011
|
January 27, 2011 |
Approved Final RCRA Facility Investigaton Work Plan, Parcels 12,14, and 25, Fort Wingte Depot Activity. McKinley County, New Mexico 27 June 2008 |
November 30, 2010 |
Soil Background Study and Data Evaluation Report, Version 2 Final October 13, 2010 |
September 21, 2010 |
Installation Action Plan, FY 2009, September 30, 2009
|
August 31, 2010 |
Fort Wingate Depot Activity Facility-Wide Ground Water Periodic Monitoring Report for October 2009 to January 2010, July 1, 2010
Survey of Buildings in the Administration and Workshop Areas Fort Wingate Depot Activity Mckinley County, New Mexico, April 9, 2008.
|
July 20, 2010 |
Final Stormwater Pollution Prevention Plan, Building Decontamination and Demolition, June 28, 2010
Final- NMED Revised RCRA Facility Investigation Work Plan Parcel 6, April 30, 2010
Final- NMED Revision RCRA Facility Investigation Work Plan Parcel 23, April 6, 2010
Soil Background Study and Data Evaluation Report Final, March 1, 2010
Final Historical Information Report Parcel 23, April 27, 2009
|
June 28, 2010 |
Final of the Release Assessment Report for Parcel 12 and Parcel 14, April 2010. Apr. 1, 2010
Work Plan – Background Study and Geochemical Evaluation (Revision 0) FINAL – Jan. 1, 2009
Interim Facility-Wide Ground Water Monitoring Plan Draft, Oct. 23, 2006
Base Realignment and Closure (BRAC) Cleanup Plan, Version 3, April 4, 2006
|
June 25, 2010 |
Facility-Wide Groundwater Periodic Monitoring Report for April 2009 to July 2009, Version 1 - FWDA_January_1_2010 |
May 27, 2010 |
Installation of Central Heat and Air Conditioning, Building 1 - FWDA, Feb. 12, 2007
Supplemental Ground Water Investigation, Administration and TNT Leaching Beds Area - FWDA, Mar. 24, 2006
Groundwater Investigation Report Eastern Landfill – Final-FWDA, Apr. 1, 2005
|
May 25, 2010 |
Draft - Site Specific Final Report, OB/OD Detonation Unit Kickout Investigation (Appendix B-G) - FWDA, May 1, 2009
Draft – Site Specific Final Report OB/OD Unit Kickout Investigation-FWDA, Jan. 1, 2009
Site-Specific Final Report, Time –Critical Action for the Arroyo Exiting Parcel 3 – DRAFT-FWDA, December 1, 2008
Kickout Investigation Work Plan – Final-FWDA, July 9, 2008
Time Critical Removal Action Addendum to the Final Kickout Investigation Work Plan - FWDA, June 2, 2008
|
|